ISIS tunnels cause new cracks in AL- Hurriya Dam
The Department of the AL- Hurriya Dam continues to work on the maintenance of transformers for the production of electric power, and turning it into the internal network, to supply villages and pumping stations with electricity
Where there were new cracks in the body of the dam and stopped traffic (heavy machinery) to maintain the safety of citizens does not allow the passage of cars with a capacity of more than 3 tons
And the reason for these cracks are the tunnels dug by ISIS mercenaries under the road on both sides of the dam from the north-west and linking these tunnels dam in Khadiran village of next to it.
It is worth mentioning that Al-Hurriya Dam is an organizational dam that regulates the flow of water in the Euphrates River and generates electricity that feeds the neighboring areas and will return to feed these areas in the next few days after completion of maintenance and experimentation in the dam.